Customer :
AT&T Services
AT&T Services
Technical Advisors Role :
MEP and Fire Safety design
MEP and Fire Safety design
Project Description:

There were no as-built drawings available, therefore systems had to be evaluated based on our experience and knowledge and a thorough field investigation.
Various options were presented to AT&T along with associated budgets. The design team in conjunction with AT&T developed construction documents to replace the fire alarm system, modify and upgrade the mechanical and electrical systems and upgrade the plumbing system for the living quarters.
Energy reduction was a priority and was incorporated into the design documents. Energy efficient pumps, boilers, light fixtures, occupancy sensors and motors were specified. The Building Automation System (BAS) was also upgraded. New electrical panels and circuits were provided at various locations.
This project was performed in several phases over a period of time to conform within the budget restrictions.

MEP and Fire Safety design for a campus style setting associated with a training facility.
Project Size:
135,927 square feet
Project was a renovation project
Dates:
Started in September 2001 and completed in March 2002.
Final Construction completed in December 2005.